Application Plan:
Day One – Wash the floor, you should be able to wash the floor in one day. Allow floor to dry overnight.
Day Two – Apply color to entire floor, allow to dry overnight.
Day Three – Apply second colors if needed or apply more color where it needs it. – Let dry overnight
Day Four – In the morning apply first coat of E10 Epoxy sealer, go to lunch for 1 to 2 hours. Return floor should be clear and dry and then apply the second coat of E10 – Let dry overnight.
Day Five - Apply final Finish coat of W10 – for 24 hours before opening to normal traffic.
Adjust drying days in between tasks per temperatures in the room. Best temperature in the room is between 65 to 75 Degrees constant.
DIY Support:
Our YouTube videos located at SEALGREENTV channel, white papers and other materials help people learn how to seal concrete driveways, patios, parking lots, kennels, and other concrete areas. You can also call us for technical support or application questions 800-997-3873
- How to use the SealGreen Patch Cement - https://youtu.be/twEDdmZhq8Q
- How to wash the floor after grinding - https://youtu.be/UqcYSC5-Y_s?t=122 (Video show the Floor Maintainer needed to scrub the floor)
- How to apply color using the brush method - https://youtu.be/XppqSDGZHUo
- Other methods to apply color - https://youtu.be/CnT_pTsDvZs
- How to apply the SealGreen E10 Epoxy Sealer - https://youtu.be/w3FDaTQ-BNs
- How to apply SealGreen W10 Finishing Coat - https://youtu.be/B6fwrnYEVgY
Source: SealGreen Website